Hardware beam commissioning

10 February - 22 March

2x slots @ 4h requested, spaced by a few days by Verena 2025-01-14.

We have slots for Monday 10 March and Wednesday 12 March, no supercycle changes allowed (parasitic studies).

  • Follow up FESA class status with Matthias and Carlo [priority:: high] [due:: 2025-01-21] [completion:: 2025-01-29]
  • Set up meeting with Kevin for implementing dB dI makerule for Real-time control channel[due:: 2025-01-14] [priority:: high] [completion:: 2025-02-04]

Beam commissioning

23 February - 10 March 11 March - 17 March SPS Scrubbing 25 March - 28 March + 2 April - 9 April SPS NA Beam Commissioning

10 April Physics start

  • 18th March

Package versions

transformertf v0.8 sps-app-hysteresis v0.1 sps-mlp-hysteresis-compensation v0.4.1 hystcomp-utils 0.2.1