A dedicated session is required to study the eddy current decays in the SPS ring based on the results from Parallel MD 2024-11-25. This should take place during the SPS Beam Commissioning 2025.
- Schedule eddy current decay studies for beam commissioning [priority:: high] [due:: 2025-02-01] [completion:: 2025-01-21]
The design of the eddy current studies MD will be carried out on 2025-02-04 09:00-12:00 in parallel to the 2025-02-03 - IPP MD days 2025.
This study follows BPMs during MD 2024-11-29.