Meeting overview
To report
- Constructed Quadrupole measurement campaign 4 waveforms to measure.
- Many cycles to measure - impossible to measure all. Where are we on
- Started Pretraining on field simulations and hyperparameter optimizations.
- Use of Neptune for project tracking.
- Initial efforts on MLST paper.
- Preparation of 2025-02-03 - IPP MD days 2025 talk.
- Design of Quadrupole inference information flow .
Outcome
- Fluxmeters to be tested starting Feb 10
- 2x NMRs, one for low field and one for high field
Action
- Investigate Model to reach correction. [priority:: low] [completion:: 2025-02-27]
- Investigate differentiable Preisach model on for model accuracy only on MBA measurements [priority:: high] [due:: 2025-01-29] [completion:: 2025-01-31]
Resolved with Fitting to MBA data
- Ask Kevin to add BHYS for MQ [priority:: high] [due:: 2025-03-01] [start:: 2025-02-15] [completion:: 2025-03-10]