Meeting with Carlo and Vincenzo to discuss future of work in TM.

Topics

  • Quadrupole vacuum pipe

    • Can we fit them in the lab?
    • If not, will it work with PCB coils?
    • We will need this for 6 and 8 poles
  • Quadrupole measurements

    • Delayed until after operational dipole test complete mid-march.
  • Additional measurements for dipoles

    • Verify pre-cycle performance during HW commissioning in W9.
  • Marco’s simulation code

    • What’s the difference between it and measurements?
  • Operational tests

    • Dipoles will be tested during Beam commissioning W10-12 in dedicated MDs.
  • IPAC paper due mid-April.

Minutes

  • Shape future for hysteresis compensation and simulation in TM section
  • Parts of the measurement systems arrived for 6 and 8 poles
  • Use beam positioning system to evaluate vacuum pipe usage
  • Proposed new measurement coils for quads expensive (0.5 M)
  • PCB coils planned do not fit into vacuum pipe (or is not taken into account)
  • Dedicated person coming for vacuum pipe investigation
  • Try to measure dipole field without vacuum chamber
  • Joint update meeting every two weeks.