📣 Agenda items

HW comissioning week 7-9 (12 feb forward), additional measurements
Beam comissioning from 1 March
Tests week 10-12 for hyst comp “operational tests”
Figure out a base model, lstm, tsmixer, transformer
Train on Marco’s hysteresis data

^ primarily for beam comissioning

Do quad measurements later to free up time for dipoles

verify pre-cycle
verify error accumulation

low priority; can we correct only eddy current at flats bottom
after korea deal with quadrupoles

IPAC paper in May + poster, in good state by mid-April

☑️ Action items

  • Check if we can add vacuum pipe to quadrupole magnets [completion:: 2024-04-15]
  • Check if PCB coils fit in quads, when they will be in production [completion:: 2024-04-15]