📣 Agenda items
HW comissioning week 7-9 (12 feb forward), additional measurements
Beam comissioning from 1 March
Tests week 10-12 for hyst comp “operational tests”
Figure out a base model, lstm, tsmixer, transformer
Train on Marco’s hysteresis data
^ primarily for beam comissioning
Do quad measurements later to free up time for dipoles
verify pre-cycle
verify error accumulation
low priority; can we correct only eddy current at flats bottom
after korea deal with quadrupoles
IPAC paper in May + poster, in good state by mid-April
☑️ Action items
- Check if we can add vacuum pipe to quadrupole magnets [completion:: 2024-04-15]
- Check if PCB coils fit in quads, when they will be in production [completion:: 2024-04-15]