Double check quads vacuum pipe PCB coils fit in vacuum pipe?
HW comissioning week 7-9 (12 feb forward), additional measurements Beam comissioning from 1 March Tests week 10-12 for hyst comp “operational tests” Figure out a base model, lstm, tsmixer, transformer Train on Marco’s hysteresis data
^ primarily for beam comissioning
Do quad measurements later to free up time for dipoles
verify pre-cycle verify error accumulation
low priority; can we correct only eddy current at flats bottom after korea deal with quadrupoles
IPAC paper in May + poster, in good state by mid-April